General News
- ADC and ATLAS Computing News [20110829]
- ADC Weekly meeting
- LFC Consolidation going well
- DB backend moved from LCGR to ADCR. Took about 2.5 hours. New front-end: prod-lfc-atlas.cern.ch (3 hosts). ToA needs to be propagated and some services need to be updated.
- Tests with SARA and IN2P3. SARA in 2 weeks? Not a clear plan for the other 13 sites yet. TRIUMF could be earlier if we like? BNL one of the last due to mySQL + T2 issues.
- Question to T2's about new data placement and if there are any issues (been about 2 months)
- During reprocessing campaign, IN2P3 saw a dcache bug. 1 file request can open many (10, 20,... up to 160 connections) which can block new connections to a pool. They are running dcache 1.9.5-24 or higher. Also mentioned that dcap client version is 2.47.5 is buggy and they are using 2.47.2-0.
- No LHC data taking since Aug 23 (MD period).
- Phase I release 17 data reprocessing completed - took two weeks.
- ESD will stay on disk for a month.
- Merged AOD/DESD distribution started on Wednesday (2 primary at T1's) and now complete.
-

- BNL shutdown due to hurricane. Back online now, but delays in planned pnfs to chimera migration. Some discussion about whether it is necessary to put T2's offline when their corresponding T1 goes offline. The claim is that Panda should be able to handle this well.
- FTS sites are reminded to update configuration for new T2Ds: https://twiki.cern.ch/twiki/bin/view/Atlas/DDMOperationsFTS#T2Ds_channels
- Some discussion about procedure to submit ATLAS related talks to CHEP2012 (NYC, May 21-25, 2012) (Computer Speaker Committee)
- CA Cloud Squad Actions [20110816]
- DaTRI requests approved / processed (last week)
| SITE |
NumRequests |
NumDatasets |
NumSubscribed |
SizeofAllDatasets (GB) |
| AUSTRALIA-ATLAS-LOCALGROUPDISK |
0 |
0 |
0 |
0 |
| AUSTRALIA-ATLAS_SCRATCHDISK |
15 |
798 |
796 |
1241 |
| CA-SCINET-T2_LOCALGROUPDISK |
41 |
85 |
85 |
3000 |
| CA-SCINET-T2_PHYS-TOP |
0 |
0 |
0 |
0 |
| CA-VICTORIA-WESTGRID-T2_LOCALGROUPDISK |
0 |
0 |
0 |
0 |
| CA-VICTORIA-WESTGRID-T2_PHYS_EXOTICS |
0 |
0 |
0 |
0 |
| SFU-LCG2_LOCALGROUPDISK |
2 |
3 |
3 |
43 |
| SFU-LCG2_PHYS-SM |
0 |
0 |
0 |
0 |
| TRIUMF-LCG2_LOCALGROUPDISK |
3 |
6 |
6 |
981 |
| TRIUMF-LCG2_SCRATCHDISK |
0 |
0 |
0 |
0 |
| TRIUMF-LCG2_PERF-TAU |
0 |
0 |
0 |
0 |
| TOTAL |
61 |
892 |
890 |
5267 |
-
- Declared Downtimes
- CA-SCINET-T2/ UNSCHEDULED downtime (OUTAGE) [22-08-2011 19:00 to 23-08-2011 16:00 UTC] - Crack in main cooling pipe detected and emergency shutdown for repair.
- CA-SCINET-T2/ UNSCHEDULED downtime (OUTAGE) [24-08-2011 07:20 to 25-08-2011 05:00 UTC] - Control box in cooling system failed bringing down the datacentre.
- TRIUMF-LCG2/ SCHEDULED downtime (OUTAGE) [24-08-2011 17:00 to 24-08-2011 20:00 UTC] - Migrate lcg CE to CREAM CE
- CA-SCINET-T2 UNSCHEDULED downtime (OUTAGE) [30-08-2011 13:00 to 31-08-2011 23:59 UTC] - Shutdown of data centre cooling to repair another leaky valve on the primary water loop
- CA-MCGILL-CLUMEQ-T2/ UNSCHEDULED downtime (OUTAGE) [30-08-2011 00:00 to 07-09-2011 00:00 UTC] - extension of the downtime to allow time for restallation.
- ATLAS Site Exclusion Savannah entries [20110621]
- HammerCloud autoexclusions
- other cloud squad related savannah and / or ROC ggus tickets [20110705]
- Open Issues and Ongoing Discussions
- Sites should be providing the April 2011 storage pledge. [see 20110315 report.
- CREAM CE deployment preparations
- HammerCloud [20110531]
- Security News [20110621]
- [20110524] UVic and Toronto participated in SSC5 (23 May - 03 June 2011) - final reports to be sent to SSC5
- [20110616] EGI CSIRT ADVISORY [EGI-ADV-20110615-02] Vulnerability for LRMS (details to be posted later)
- gLite News [20110705]
- [20110705] [https://operations-portal.egi.eu/broadcast/archive/id/420][EGI Trust Anchor release 1.40-1] is now final - please install.
- [20110504] [https://operations-portal.egi.eu/broadcast/archive/id/378 ][gLite 3.2 WN release] has an important known issue detailed here: http://glite.cern.ch/glite-WN/known_issues
- [20110627] New IGTF distribution (certificates) and version 3 of the CRL retrieval tool Fetch-crl https://dist.eugridpma.info/distribution/util/fetch-crl3/
. Version 1.39 was updated to 1.40 on 2011-06-28.
- [20110628] [https://operations-portal.egi.eu/broadcast/archive/id/410][gLite 3.2 update 30 release] The highlights of the update are:
- New version of glite-BDII_top
- New version of glite-CREAM (to support changes for SGE)
- New version of glite-LB
- New version of glite-SGE_utils
- ROC_Canada News [20110809]
- Squid Deployment [20110329]
SAM Results
- site service status via Gridview
- Please check your site
- August 17-30, 2011





- August 2011 Detailed Site Information (valid until 20110831):
- TRIUMF-LCG2
- Australia-ATLAS
- CA-ALBERTA-WESTGRID-T2
- CA-SCINET-T2
- CA-VICTORIA-WESTGRID-T2
- SFU-LCG2
APEL Accounting
- ACTION ITEM FOR SITES: Sites please regularly check and confirm that your historical APEL data has been published and looks correct when comparing with batch system utilization
APEL Publishing Status

APEL Accounting Results

APEL Synchronization Test Links
Site Reports
Alberta
Recent Issues
- summary of this weeks Savannah bugs and GGUS tickets for site:
- production job issues
- See "Production" Activities section below
- analysis job issues
- See "Notes" section below
Outstanding Issues
Recent Issues
- summary of this weeks Savannah bugs and GGUS tickets for site:
- production job issues
- See "Production" Activities section below
- analysis job issues
- See "Notes" section below
Outstanding Issues
Victoria
Recent Issues
- summary of this weeks Savannah bugs and GGUS tickets for site:
- production job issues
- See "Production" Activities section below
- analysis job issues
- see "Notes" section below
Outstanding Issues
Toronto
Recent Issues
- summary of this weeks Savannah bugs and GGUS tickets for site:
- production job issues
- See "Production" Activities section below
- analysis job issues
- See "Notes" section below
Outstanding Issues
McGill
Recent Issues
Outstanding Issues
Recent Issues
- production job issues
- See "Production" Activities section below
- analysis job issues
- see "Notes" section below
Outstanding Issues
Australia-ATLAS
Recent Issues
- summary of this weeks Savannah bugs and GGUS tickets for site:
- production job issues
- See "Production" Activities section below
- analysis job issues
- See "Notes" section below
Outstanding Issues
Production



Summary
- NOTE: ARDA ProdSys Dashboard has stopped being used by ADCoS team due to information updating issues with the interface. The historical job usage information is to appear separately within ARDA and is being validated. This will be used in the future for information presented here.
- Within the CA Cloud and Worldwide (Panglia
View):
--
LeslieGroer - 2011-08-29