Tier1 and Tier-2 Weekly Report 2014-11-11
General News
- ADC and ATLAS Computing News [20141111]
- ADC Weekly meeting
- Rucio Migration
- Still planning switchover for production system Nov 24-29 - planning 12 hour downtime
- Some metadata changes needed beforehand - been agreed to by ProdSysII and PanDA
- Requires database intervention
- Planned for Thursday morning - only Rucio datasets will be affected (unavailable) for approx. 30mins
- DQ2 client testing
- Few backward incompatibilities already reported by HC team and fixed
- Doug Benjamin is now testing DQ2 client from end user POV
- If an incompatibility cannot be fixed it will be mentioned in migration FAQ
- The migration FAQ will be linked from the top of DQ2ClientsHowTo
- DQ2 to Rucio migration
- Implemented on DB level (PLSQL procedure)
- Moves dataset definition from DQ2 (central catalog) to Rucio, including metadata
- Creates rules+locks in Rucio for DQ2 replicas
- Being tested on intergration instance of Rucio
- First real datasets will be migrated Wednesday morning (old logs)
- Ops will check that migrated datasets are visible and have proper replicas/rules/attributes
- Batch migration will start Thursday or Friday
- Further migration steps in https://docs.google.com/document/d/1CKeF0QWN01fAttzrcbHqwlL4wEjTyEZ82Us9ejakOKY
- TAPE staging
- Transferring to T1 tape (with FTS3) is tested (with PIC)
- Stage-in requests + transfers fixed last week
- More testing needed - Vincenzo will ask T1s to remove few files from disk cache, so we are sure the whole chain from tape to disk is tested for all T1s
- Accounting
- The dumps from Rucio to accounting dashboard are almost ready
- Still some hadoop technical issues to resolve
- Plan to run the dumps from DQ2 and Rucio in parallel for one week to compare the results
- Popularity
- Trace records are now reported from pilot to Rucio and also DQ2 - pilot not in production yet
- Status of Derivation Production and ProdSys2 Commissioning
- 8 TeV production launched October 20th. Still active tasks in system after 3 weeks
- Were some grid issues in the first week but even with single carriage train, this seems too long - some discussion and investigation by GDP
- 13 TeV production stopped after very slow read of xAODs (about a factor 20-100 slower than for 8 TeV files, for both ROOT and athena) due to the ROOT version in 19.1.4.2, merging took very long (up to 24 hours for 1 GB of output) in validation tasks.
- Users have been informed to use newer ROOT releases (Root-5.34.22 or newer) as provided in the latest Analysis releases starting from 2.0.16 in analyzing xAODs directly and not wait for derivations for the ATLAS Physics Workshop next week
- Tasks were slow to start, one problem identified, missing installations in ND cloud. GDP and the cloud support are investigating.
- Will need a new cache for the ROOT patch. AODFix+trigger fix is also planned to be put in for the upcoming production - to be launched this week.
- Last week of November is fine for decommissioning ProdSys1
- Derivation production only implemented in ProdSys2
- Legacy group production moved to ProdSys2 on Oct. 24th, no problems reported so far
- CA Cloud Squad Actions
- Open Issues and Ongoing Discussions
- WLCG and General Computing News
- Security News
- gLite/EMI News
- ROC_Canada News
ABCD Determination and Monitoring
SSB Results
SAM Results (based on VO tests)
APEL Accounting
- ACTION ITEM FOR SITES: Sites please regularly check and confirm that your historical APEL data has been published and looks correct when comparing with batch system utilization
APEL Synchronization Test Links
Production and Usage Status
--
Leslie Groer - 2014-11-11
Comments
This topic: AtlasCanada
> WebHome >
GridActivities >
ATLASCanadaTier-2Operations > T2WeeklyReport20141111
Topic revision: r1 - 2014-11-11 - LeslieGroer