ANALY_SFU (eff about 85% but too few jobs for black/white list determination)
Plan: switch off template 508 (Athena 17.2.7.6 Reco NTUP_SMWZ) and replace it with 729 tomorrow
After Easter, also update the other 2 AFTs (will be announced in ADC weekly)
CRC/ADCoS report
Some dicussion about complaints in Phys Coord that users can't get their outputs
Could make double copies (i.e. ask rucio to make a copy in scratch somewhere else). Some concern about number of files being transferred
Phys Coord question about MC15c competing with other high priority tasks (e.g. HI estimated to need 2 months for reprocessing). Maybe limit the number of cores used (20k?) - may not be very effective. Have sharing as well but again may not work as expected.
LHC : Powering test
Running slots : Grid running above 200k the last week.
MC15c running at good speed, about 70-100 Mevts per day (pile)
New configuration (replacing the problematic one is under test)
ACTION ITEM FOR SITES: Sites please regularly check and confirm that your historical APEL data has been published and looks correct when comparing with batch system utilization
See example steps circulated by D. Qing (20100406)